Delivered precision execution within a compressed timeframe. Zucchini Busbar was custom-fabricated and delivered, ensuring uninterrupted progress on-site.
- Location: Nagercoil, Tamil Nadu
- Objective: To commission the electrical backbone as per the schedule and energise the hospital with zero delays.
- Products: DMX3 (3 is superscript) ACB, DPX3 (3 is superscript) MCCB, Zucchini busbars Trunking systems, Meters, Contactors and Capacitors.
A Tier IV data center in Mumbai partnered with a global GPU manufacturer to offer GPU-as-a-Service and host India’s fastest AI supercomputer. This led to a significant increase in heat output, with GPU racks reaching up to 50kW. Legrand deployed 192 ColdLogik RDHx units using air-assisted liquid cooling to manage this heat efficiently. The solution achieved a PUE of 1.35, minimized infrastructure footprint, and enabled scalable, energy-efficient operations. The entire deployment was completed in just 45 days, showcasing Legrand’s commitment to agile, future-ready data center solutions.
Despite project's complexity, Legrand team provided full electrical and ELV deployment within scheduled window, completing installation across 66 rooms, public spaces, and service areas with zero major delays